🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Goldwick Solar Farm

Goldwick Solar Farm is a 200 MW solar + storage request withdrawn in the CAISO interconnection queue, in Stanislaus County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedMar 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1377
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Salado Substation 115kV
Location
Stanislaus County, California
Technology
Solar: 100 MW · Battery: 100 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 May 2017
Proposed online date
October 2020
Withdrawn
March 2018

Location

Marker shows the centre of Stanislaus County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Stanislaus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem