SOLAR Β· CAISO

Curry Solar

Curry Solar is a 71.5 MW solar request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedMar 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1372
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Schindler Substation 70kV
Location
Fresno County, California
Technology
Solar: 71.5 MW
Total requested
71.5 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 May 2017
Proposed online date
November 2020
Withdrawn
March 2018

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Fresno County