SOLAR Β· CAISO

Rubita

Rubita is a 102 MW solar request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedMay 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1415
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Kramer-Inyokern-Randsburg No.1 115kV
Location
San Bernardino County, California
Technology
Solar: 102 MW
Total requested
102 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 May 2017
Proposed online date
October 2023
Withdrawn
May 2020

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in San Bernardino County