Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,646350.1 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,646 requests · page 9 of 33
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3945, Washtenaw County
Solar
245 MWIn study Washtenaw, MIMISO Apr 2025target 2030
Solar project J4147, Clay County
Solar
245 MWIn study Clay, MNMISO Oct 2025target 2030
Solar project J4001, Marion County
Solar
245 MWIn study Marion, MOMISO Apr 2025target 2030
Solar project J3949, Scott County
Solar
245 MWIn study Scott, ILMISO Apr 2025target 2030
Solar project J4148, Clay County
Solar
245 MWIn study Clay, MNMISO Oct 2025target 2030
Solar project J2849, Pulaski County
Solar
245 MWIn study Pulaski, INMISO Sep 2022target 2025
Solar project J3961, Lincoln County
Solar
245 MWIn study Lincoln, MNMISO Apr 2025target 2030
Solar project J2870, Sawyer County
Solar
244 MWIn study Sawyer, WIMISO Sep 2022target 2026
Battery storage project J4117, Goodhue County
Battery storage
240 MWIn study Goodhue, MNMISO Sep 2025target 2030
Solar + storage project J3985, Polk County
Solar + storage
240 MWIn study Polk, TXMISO Nov 2024target 2030
Solar project J1067, Jasper County
Solar
240 MWUnder construction Jasper, INMISO Mar 20182024
Battery storage project J2567, Oceana County
Battery storage
240 MWIn study Oceana, MIMISO Sep 2022target 2025
Solar project J2149, Saline County
Solar
240 MWIn study Saline, ARMISO Nov 2021target 2024
Replacing 258MW ERIS gas/oil with 237MW ERIS Natural Gas/oil; Wheaton 1-4
Gas
237 MWIn study Chippewa, MNMISO Mar 2024target 2025
Onshore wind project J3856, Wabash County
Onshore wind
235 MWIn study Wabash, ILMISO Dec 2024target 2030
Solar project J3021, Lyon County
Solar
235 MWIn study Lyon, MNMISO Sep 2022target 2027
Gas project J3289, Sherburne County
Gas
235 MWIn study Sherburne, MNMISO Apr 2024target 2026
Onshore wind project J4068, Marshall County
Onshore wind
232 MWIn study Marshall, IAMISO Oct 2025target 2030
Onshore wind project J2104, Murray County
Onshore wind
230 MWIn study Murray, MNMISO Sep 2025target 2024
Onshore wind project J2342, Worth County
Onshore wind
230 MWIn study Worth, IAMISO Sep 2022target 2027
Onshore wind project J3864, Shiawassee County
Onshore wind
230 MWIn study Shiawassee, MIMISO Dec 2024target 2028
Solar project J2317, Ouachita Parish County
Solar
225 MWIn study Ouachita Parish, LAMISO Dec 2021target 2027
Solar project J2673, Clare County
Solar
225 MWIn study Clare, MIMISO Sep 2022target 2025
Onshore wind project J3830
Onshore wind
225 MWIn study ILMISO Apr 2024target 2028
Battery storage project J3727, Madison County
Battery storage
225 MWIn study Madison, ILMISO Apr 2024target 2028
Solar project J3838, Ingham County
Solar
225 MWIn study Ingham, MIMISO Apr 2024target 2028
Solar project J2668, Mason County
Solar
225 MWIn study Mason, MIMISO Sep 2022target 2025
Solar project J3139, Holmes County
Solar
225 MWIn study Holmes, MSMISO Sep 2022target 2026
Battery storage project J3696, Montcalm County
Battery storage
225 MWIn study Montcalm, MIMISO Apr 2024target 2026
Solar project J1502, Juneau County
Solar
225 MWAgreement signed Juneau, WIMISO Jun 2020target 2026
Solar + storage project J3528, Jasper County
Solar + storage
225 MWIn study Jasper, ILMISO Apr 2024target 2026
Solar project J3479, Rapides Parish County
Solar
225 MWIn study Rapides Parish, LAMISO Apr 2024target 2027
Solar project J4151, Redwood County
Solar
225 MWIn study Redwood, MNMISO Oct 2025target 2030
Solar project J1034, Stoddard County
Solar
225 MWUnder construction Stoddard, MOMISO Mar 2018target 2024
Solar project J2670, Mason County
Solar
223 MWIn study Mason, MIMISO Sep 2022target 2025
Solar + storage project J2924, Columbia County
Solar + storage
222 MWIn study Columbia, ARMISO Sep 2022target 2027
Solar project J4051, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project J2554, Putnam County
Solar
220 MWIn study Putnam, ILMISO Sep 2022target 2026
Solar project J3418, Sangamon County
Solar
220 MWIn study Sangamon, ILMISO Apr 2024target 2028
Onshore wind project J3496, Sanilac County
Onshore wind
220 MWIn study Sanilac, MIMISO Apr 2024target 2027
Solar project J3495, Greene County
Solar
220 MWIn study Greene, INMISO Apr 2024target 2028
Solar project J2444, Van Buren County
Solar
220 MWIn study Van Buren, MIMISO Sep 2022target 2026
Replacing 220 MW of coal generation with BESS; Trenton Channel 9
Other
220 MWIn study Wayne, MIMISO Oct 2023target 2025
Battery storage project J3646, St. Clair County
Battery storage
220 MWIn study St. Clair, MIMISO Apr 2024target 2028
Solar project J2001, Newaygo County
Solar
220 MWIn study Newaygo, MIMISO Aug 2021target 2025
Solar project J4050, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project J4041, Menard County
Solar
220 MWIn study Menard, ILMISO Jun 2025target 2030
Solar project J2814, Kalamazoo County
Solar
220 MWIn study Kalamazoo, MIMISO Sep 2022target 2026
Solar project J2599, Redwood County
Solar
216 MWIn study Redwood, MNMISO Sep 2022target 2026
Solar project J3457, Arkansas County
Solar
215 MWIn study Arkansas, ARMISO Apr 2024target 2027
Page 9 of 33

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)