United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J4147, Clay County
Solar project J4147, Clay County is a 245 MW solar request in interconnection study in the MISO interconnection queue, in Clay County, Minnesota, connecting to MISSOURI RIVER ENERGY SERVICES - TRANSMISSION.
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4147
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
- Connection point (POI)
- ALEXANDRIA - BISON 345.0kV
- Location
- Clay County, Minnesota
- Technology
- Solar: 245 MW
- Total requested
- 245 MW
- Service type
- Energy only (ERIS)
- Queue status
- Active
- Entered queue
- 3 October 2025
- Proposed online date
- January 2030
Location
Marker shows the centre of Clay County; the queue data does not give exact sites.
Other requests in Clay County
- Solar project J3762, Clay CountySolar · 430 MW · in study
- Solar project J4148, Clay CountySolar · 245 MW · in study
- Onshore wind project G006, Clay CountyOnshore wind · 2.0 MW · in study
- Other project GI-0825, Clay CountyOther · 11.0 MW · built
- Onshore wind project G859, Clay CountyOnshore wind · 600 MW · withdrawn
- Onshore wind project G821, Clay CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J001, Clay CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project H099, Clay CountyOnshore wind · 150 MW · withdrawn
- Gas project GI-0109, Clay CountyGas · 50.0 MW · withdrawn
- Onshore wind project J2067, Clay CountyOnshore wind · 39.4 MW · withdrawn
- Onshore wind project G414, Clay CountyOnshore wind · 10.0 MW · withdrawn
- Onshore wind project G846, Clay CountyOnshore wind · 4.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem