United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G859, Clay County

Onshore wind project G859, Clay County is a 600 MW onshore wind request withdrawn in the MISO interconnection queue, in Clay County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2007 (completed)
  2. Withdrawn / abandonedJan 2013 (project stopped here)
  3. ConsentedJan 2013 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G859
Grid region
MISO (Midcontinent)
Connection point (POI)
Maple River 345 kV
Location
Clay County, Minnesota
Technology
Wind: 600 MW
Total requested
600 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
14 September 2007
Agreement signed
30 January 2013
Proposed online date
December 2009
Withdrawn
January 2013

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Clay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem