United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G846, Clay County

Onshore wind project G846, Clay County is a 4.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Clay County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2007 (completed)
  2. Withdrawn / abandonedFeb 2011 (project stopped here)
  3. ConsentedFeb 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G846
Grid region
MISO (Midcontinent)
Connection point (POI)
GRE Pelican Lake - Tansem 41.6 kV
Location
Clay County, Minnesota
Technology
Wind: 4.0 MW
Total requested
4.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
28 August 2007
Agreement signed
17 February 2011
Proposed online date
May 2011
Withdrawn
February 2011

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Clay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem