United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G821, Clay County

Onshore wind project G821, Clay County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Clay County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2007 (completed)
  2. Withdrawn / abandonedJan 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G821
Grid region
MISO (Midcontinent)
Connection point (POI)
OTP Sheyenne - Audubon 230 kV
Location
Clay County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
19 July 2007
Withdrawn
January 2015

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Clay County