United States › Grid › Interconnection queues › Minnesota

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Minnesota — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown48280.5 GW
Active in queue28.4 GW155 requests
Agreement signed309 MW9 requests
Withdrawn48280.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

482 requests · page 8 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project H065, Renville County
Onshore wind
40.0 MWWithdrawn / abandoned Renville, MNMISO Jun 2008target 2010
Solar project J322, Renville County
Solar
40.0 MWWithdrawn / abandoned Renville, MNMISO Jan 2014target 2014
Onshore wind project H057, Jackson County
Onshore wind
40.0 MWWithdrawn / abandoned Jackson, MNMISO Jun 2008target 2011
Onshore wind project H051, Redwood County
Onshore wind
40.0 MWWithdrawn / abandoned Redwood, MNMISO Jun 2008target 2011
Onshore wind project J574, Kandiyohi County
Onshore wind
40.0 MWWithdrawn / abandoned Kandiyohi, MNMISO May 2016target 2017
Solar project J1001, Lincoln County
Solar
40.0 MWWithdrawn / abandoned Lincoln, MNMISO Mar 2018target 2020
Onshore wind project H055, Redwood County
Onshore wind
40.0 MWWithdrawn / abandoned Redwood, MNMISO Jun 2008target 2011
Solar project J905, Pipestone County
Solar
40.0 MWWithdrawn / abandoned Pipestone, MNMISO Jun 2017target 2020
Onshore wind project H059, Nobles County
Onshore wind
40.0 MWWithdrawn / abandoned Nobles, MNMISO Jun 2008target 2011
Onshore wind project H068, Rice County
Onshore wind
40.0 MWWithdrawn / abandoned Rice, MNMISO Jun 2008target 2010
Solar project J784, Renville County
Solar
40.0 MWWithdrawn / abandoned Renville, MNMISO Nov 2016target 2018
Solar project J345, Waseca County
Solar
40.0 MWWithdrawn / abandoned Waseca, MNMISO May 2014target 2016
Onshore wind project H056, Rice County
Onshore wind
40.0 MWWithdrawn / abandoned Rice, MNMISO Jun 2008target 2011
Onshore wind project H063, Mcleod County
Onshore wind
40.0 MWWithdrawn / abandoned Mcleod, MNMISO Jun 2008target 2011
Battery storage project J1230, Wadena County
Battery storage
40.0 MWWithdrawn / abandoned Wadena, MNMISO Apr 2019target 2023
Onshore wind project H054, Redwood County
Onshore wind
40.0 MWWithdrawn / abandoned Redwood, MNMISO Jun 2008target 2011
Onshore wind project H067, Kandiyohi County
Onshore wind
40.0 MWWithdrawn / abandoned Kandiyohi, MNMISO Jun 2008target 2009
Solar project J1098, Jackson County
Solar
40.0 MWWithdrawn / abandoned Jackson, MNMISO Mar 2018target 2022
Onshore wind project G576, Rock County
Onshore wind
40.0 MWWithdrawn / abandoned Rock, MNMISO Dec 2005target 2007
Onshore wind project J288, Kandiyohi County
Onshore wind
40.0 MWWithdrawn / abandoned Kandiyohi, MNMISO Jul 2013target 2019
Onshore wind project J136, Fillmore County
Onshore wind
40.0 MWWithdrawn / abandoned Fillmore, MNMISO Feb 2009target 2013
Onshore wind project J2067, Clay County
Onshore wind
39.4 MWWithdrawn / abandoned Clay, MNMISO Sep 2021target 2024
Onshore wind project H064, Sibley County
Onshore wind
39.0 MWWithdrawn / abandoned Sibley, MNMISO Jun 2008target 2011
Onshore wind project H061, Goodhue County
Onshore wind
39.0 MWWithdrawn / abandoned Goodhue, MNMISO Jun 2008target 2010
Onshore wind project J180, Goodhue County
Onshore wind
39.0 MWWithdrawn / abandoned Goodhue, MNMISO Nov 2010target 2012
Onshore wind project H062, Goodhue County
Onshore wind
39.0 MWWithdrawn / abandoned Goodhue, MNMISO Jun 2008target 2011
Solar project J367, Goodhue County
Solar
39.0 MWWithdrawn / abandoned Goodhue, MNMISO May 2014target 2016
Onshore wind project H047, Steele County
Onshore wind
35.0 MWWithdrawn / abandoned Steele, MNMISO Jun 2008target 2011
Solar project J769, Renville County
Solar
33.0 MWWithdrawn / abandoned Renville, MNMISO Nov 2016target 2019
Solar project J803, Lyon County
Solar
32.5 MWWithdrawn / abandoned Lyon, MNMISO Jun 2017target 2023
Solar project J1038, Grant County
Solar
32.5 MWWithdrawn / abandoned Grant, MNMISO Mar 2018target 2020
Onshore wind project G626, Brown County
Onshore wind
32.0 MWWithdrawn / abandoned Brown, MNMISO Apr 2006target 2007
Onshore wind project G628, Brown County
Onshore wind
32.0 MWWithdrawn / abandoned Brown, MNMISO May 2006target 2007
Battery storage project J1054, Goodhue County
Battery storage
30.0 MWWithdrawn / abandoned Goodhue, MNMISO Mar 2018target 2021
Onshore wind project G797, Martin County
Onshore wind
30.0 MWWithdrawn / abandoned Martin, MNMISO May 2007target 2007
Onshore wind project J087, Kandiyohi County
Onshore wind
30.0 MWWithdrawn / abandoned Kandiyohi, MNMISO Oct 2009target 2012
Onshore wind project J223, Mower County
Onshore wind
30.0 MWWithdrawn / abandoned Mower, MNMISO Aug 2011target 2012
Battery storage project J1968, Polk County
Battery storage
30.0 MWWithdrawn / abandoned Polk, MNMISO Aug 2021target 2026
Onshore wind project G640, Todd County
Onshore wind
30.0 MWWithdrawn / abandoned Todd, MNMISO May 2006target 2007
Other project J175, St. Louis County
Other
30.0 MWWithdrawn / abandoned St. Louis, MNMISO Nov 2010target 2011
Solar project J1511, Chisago County
Solar
26.0 MWWithdrawn / abandoned Chisago, MNMISO Jun 2020target 2023
Onshore wind project J006, Nicollet County
Onshore wind
25.0 MWWithdrawn / abandoned Nicollet, MNMISO Oct 2008target 2012
Onshore wind project J216, Mower County
Onshore wind
25.0 MWWithdrawn / abandoned Mower, MNMISO Jun 2011target 2013
Onshore wind project J1800, Mower County
Onshore wind
25.0 MWWithdrawn / abandoned Mower, MNMISO Jun 2020target 2023
Other project G950, St. Louis County
Other
25.0 MWWithdrawn / abandoned St. Louis, MNMISO Jan 2008target 2009
Solar project J330, Lyon County
Solar
24.8 MWWithdrawn / abandoned Lyon, MNMISO May 2014target 2019
Onshore wind project G688, Murray County
Onshore wind
24.0 MWWithdrawn / abandoned Murray, MNMISO Oct 2006target 2008
Onshore wind project J045, Pipestone County
Onshore wind
23.1 MWWithdrawn / abandoned Pipestone, MNMISO May 2009target 2010
Other project G130, Murray County
Other
22.0 MWWithdrawn / abandoned Murray, MNMISO Sep 2001target 2007
Other project G683, Hennepin County
Other
22.0 MWWithdrawn / abandoned Hennepin, MNMISO Sep 2006target 2003
Page 8 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)