United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G640, Todd County

Onshore wind project G640, Todd County is a 30.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Todd County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2006 (completed)
  2. Withdrawn / abandonedApr 2013 (project stopped here)
  3. ConsentedApr 2013 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G640
Grid region
MISO (Midcontinent)
Connection point (POI)
MP Long Prairie - Wing Rive 115kV
Location
Todd County, Minnesota
Technology
Wind: 30.0 MW
Total requested
30.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
22 May 2006
Agreement signed
3 April 2013
Proposed online date
October 2007
Withdrawn
April 2013

Location

Marker shows the centre of Todd County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Todd County