ONSHORE WIND Β· MISO

Onshore wind project J005, Todd County

Onshore wind project J005, Todd County is a 17.5 MW onshore wind request withdrawn in the MISO interconnection queue, in Todd County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2008 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. ConsentedAug 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J005
Grid region
MISO (Midcontinent)
Connection point (POI)
R34WT133N, Section 7, Bartlett Twp
Location
Todd County, Minnesota
Technology
Wind: 17.5 MW
Total requested
17.5 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
24 October 2008
Agreement signed
23 August 2012
Proposed online date
December 2009
Withdrawn
August 2012

Location

Marker shows the centre of Todd County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Todd County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem