United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project J045, Pipestone County
Onshore wind project J045, Pipestone County is a 23.1 MW onshore wind request withdrawn in the MISO interconnection queue, in Pipestone County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2009 (completed)
- Withdrawn / abandonedDec 2012 (project stopped here)
- ConsentedDec 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J045
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- RockRiver - South Ridge 69 kV
- Location
- Pipestone County, Minnesota
- Technology
- Wind: 23.1 MW
- Total requested
- 23.1 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 18 May 2009
- Agreement signed
- 27 December 2012
- Proposed online date
- June 2010
- Withdrawn
- December 2012
Location
Marker shows the centre of Pipestone County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Pipestone County
- Onshore wind project G621, Pipestone CountyOnshore wind Β· 20.0 MW Β· agreement signed
- Onshore wind project G081, Pipestone CountyOnshore wind Β· 1.0 MW Β· agreement signed
- Solar project J1620, Pipestone CountySolar Β· 125 MW Β· in study
- Onshore wind project J426, Pipestone CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project J558, Pipestone CountyOnshore wind Β· 9.2 MW Β· built
- Onshore wind project G285, Pipestone CountyOnshore wind Β· 9.0 MW Β· built
- Onshore wind project G278, Pipestone CountyOnshore wind Β· 8.0 MW Β· built
- Onshore wind project G382, Pipestone CountyOnshore wind Β· 8.0 MW Β· built
- Onshore wind project G397, Pipestone CountyOnshore wind Β· 5.0 MW Β· built
- Onshore wind project G185, Pipestone CountyOnshore wind Β· 4.0 MW Β· built
- Onshore wind project G041, Pipestone CountyOnshore wind Β· 2.0 MW Β· built
- Onshore wind project G398, Pipestone CountyOnshore wind Β· 2.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem