🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G081, Pipestone County

Onshore wind project G081, Pipestone County is a 1.0 MW onshore wind request with a signed interconnection agreement in the MISO interconnection queue, in Pipestone County, Minnesota.

Queue statusConsented
  1. PlanningQueued Feb 2001 (completed)
  2. ConsentedFeb 2004 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2003 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
G081
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Pipestone County, Minnesota
Technology
Wind: 1.0 MW
Total requested
1.0 MW
Study phase
IA Executed
Queue status
Active
Entered queue
22 February 2001
Agreement signed
10 February 2004
Proposed online date
June 2003

Location

Marker shows the centre of Pipestone County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Pipestone County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem