ONSHORE WIND · MISO

Onshore wind project G278, Pipestone County

Onshore wind project G278, Pipestone County is a 8.0 MW onshore wind request built and operating in the MISO interconnection queue, in Pipestone County, Minnesota.

Queue statusOperating
  1. PlanningQueued Dec 2002 (completed)
  2. ConsentedFeb 2005 (completed)
  3. Construction (completed)
  4. OperatingMay 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G278
Grid region
MISO (Midcontinent)
Connection point (POI)
Pipestone - Dell Rapids 69kV
Location
Pipestone County, Minnesota
Technology
Wind: 8.0 MW
Total requested
8.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
19 December 2002
Agreement signed
7 February 2005
Proposed online date
May 2007
Came online
May 2007

Location

Marker shows the centre of Pipestone County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Pipestone County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem