SOLAR Β· MISO

Solar project J322, Renville County

Solar project J322, Renville County is a 40.0 MW solar request withdrawn in the MISO interconnection queue, in Renville County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2014 (completed)
  2. Withdrawn / abandonedSep 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J322
Grid region
MISO (Midcontinent)
Connection point (POI)
69 kV bus at Sacred Heart substation
Location
Renville County, Minnesota
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
13 January 2014
Proposed online date
November 2014
Withdrawn
September 2014

Location

Marker shows the centre of Renville County; the queue data does not give exact sites.