πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project H047, Steele County

Onshore wind project H047, Steele County is a 35.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Steele County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedJun 2012 (project stopped here)
  3. ConsentedJun 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H047
Grid region
MISO (Midcontinent)
Connection point (POI)
ITC Midwest Medford Junction 69 kV Substation
Location
Steele County, Minnesota
Technology
Wind: 35.0 MW
Total requested
35.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
12 June 2008
Agreement signed
26 June 2012
Proposed online date
December 2011
Withdrawn
June 2012

Location

Marker shows the centre of Steele County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Steele County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem