United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESInterconnection queue in the USA (2017 requests) โ page 6
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Geothermal project Company HU, Churchill County Geothermal |
38.5 MW | Agreement signed |
| Starlight Solar Solar + storage |
37.4 MW | Agreement signed |
| Other project J868, Concordia Parish County Other |
37.2 MW | Under construction |
| Solar project GI-2017-52, El Paso County Solar |
36.0 MW | Agreement signed |
| Sweetleaf Solar Solar |
33.0 MW | Paused / redesign |
| Capricorn I & III repower Onshore wind ยท Nextera |
32.0 MW | Agreement signed |
| Spinel Solar Solar |
30.0 MW | Paused / redesign |
| Hydro project 323, Marion County Hydro |
27.0 MW | Agreement signed |
| Hydro project 322, Marion County Hydro |
27.0 MW | Agreement signed |
| Fluorite Solar Solar |
25.0 MW | Paused / redesign |
| Gas project 332, Shelby County Gas |
23.0 MW | Agreement signed |
| SunEast Skyline Solar LLC Solar ยท SunEast Skyline Solar LLC |
20.0 MW | In study |
| Cedar Creek Solar Solar |
20.0 MW | Paused / redesign |
| Eaton OH Solar Solar |
20.0 MW | Agreement signed |
| Walnut Solar I Solar |
20.0 MW | Agreement signed |
| Cedar Creek Solar Solar |
20.0 MW | Paused / redesign |
| Blue Creek Wind Farm Solar |
20.0 MW | Paused / redesign |
| Basalt Solar Solar |
20.0 MW | Paused / redesign |
| Fair Haven Solar Solar |
20.0 MW | Agreement signed |
| Solar project G0570, Lake County Solar |
20.0 MW | In study |
| Shaftsbury Solar Solar |
20.0 MW | Agreement signed |
| Solar project G0571, Lake County Solar |
20.0 MW | In study |
| Solar project G0572, Lake County Solar |
20.0 MW | In study |
| Raceway Solar Solar |
20.0 MW | Agreement signed |
| Raceway Solar Solar |
20.0 MW | Agreement signed |
| Battery storage project GEN-2017-117, Canadian County Battery storage |
19.8 MW | Paused / redesign |
| Onshore wind project GI-60, Gentry County Onshore wind |
18.0 MW | Agreement signed |
| East Hagerstown Solar Solar |
11.8 MW | Agreement signed |
| Battery storage project GEN-2017-198, Douglas County Battery storage |
11.6 MW | Agreement signed |
| Hydro project 320, Marion County Hydro |
11.0 MW | Agreement signed |
| Hydro project 321, Marion County Hydro |
11.0 MW | Agreement signed |
| Solar project SGI-PNM-2017-08, Luna County Solar |
11.0 MW | Agreement signed |
| Raceway Solar Solar |
10.0 MW | Agreement signed |
| Solar project IA-PNM-2017-01, Cibola County Solar ยท NextEra Energy |
10.0 MW | Agreement signed |
| Solar project SGI-PNM-2017-09, Luna County Solar |
8.3 MW | Agreement signed |
| Sweetwater 2 repower Onshore wind ยท Leeward Energy |
7.3 MW | Agreement signed |
| Desert Sky repower Onshore wind ยท DESERT SKY WIND FARM LLC |
7.2 MW | Agreement signed |
| Trent repower Onshore wind ยท TRENT WIND FARM LLC |
6.4 MW | Agreement signed |
| Hydro project 973, Franklin County Hydro ยท City of Preston |
0.4 MW | Agreement signed |
| Silver Star repower Onshore wind ยท Silver Star I Power Partners, LLC |
-7.2 MW | Agreement signed |
| Sherbino II Wind repower Onshore wind ยท Sherbino II Wind Farm LLC |
-18.0 MW | Agreement signed |
| Trinity Hills Wind repower Onshore wind ยท Trinity Hills Wind Farm LLC |
-27.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- SPP (Southwest Power Pool)66 ยท 11.8 GW
- West (non-ISO utilities)60 ยท 10.4 GW
- CAISO (California)17 ยท 8,678 MW
- ERCOT (Texas)36 ยท 5,724 MW
- MISO (Midcontinent)32 ยท 5,609 MW
- PJM (Mid-Atlantic, Midwest)44 ยท 4,774 MW
- Southeast (non-ISO utilities)28 ยท 2,517 MW
- ISO-NE (New England)3 ยท 831 MW
- NYISO (New York)6 ยท 749 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)