United States › Grid › Interconnection queues › Missouri
ONSHORE WIND · SOUTHEASTOnshore wind project GI-60, Gentry County
Onshore wind project GI-60, Gentry County is a 18.0 MW onshore wind request with a signed interconnection agreement in the Southeast interconnection queue, in Gentry County, Missouri, connecting to Associated Electric Cooperative, Incorporated.
Queue statusConsented
- PlanningQueued Apr 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-60
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Associated Electric Cooperative, Incorporated
- Connection point (POI)
- Winslow 161 kV Substation
- Location
- Gentry County, Missouri
- Technology
- Wind: 18.0 MW
- Total requested
- 18.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 4 April 2017
Location
Marker shows the centre of Gentry County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem