United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) (2022 requests) β€” page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown43582.2 GW
Active in queue82.2 GW435 requests
Agreement signed881 MW6 requests
Withdrawn56794.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

435 requests Β· page 6 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2730, Jackson County
Battery storage
150 MWIn study Jackson, MNMISO Sep 2022target 2025
Solar project J2749, Polk County
Solar
150 MWIn study Polk, MNMISO Sep 2022target 2026
Solar project J2643, Washington Parish County
Solar
150 MWIn study Washington Parish, LAMISO Sep 2022target 2027
Battery storage project J2728, Freeborn County
Battery storage
150 MWIn study Freeborn, MNMISO Sep 2022target 2025
Battery storage project J2627, Adams County
Battery storage
150 MWIn study Adams, ILMISO Sep 2022target 2025
Solar project J3134, Otsego County
Solar
150 MWIn study Otsego, MIMISO Sep 2022target 2025
Solar + storage project J3185, Effingham County
Solar + storage
150 MWIn study Effingham, ILMISO Sep 2022target 2027
Solar project J3042, St. John The Baptist Parish County
Solar
150 MWIn study St. John The Baptist Parish, LAMISO Sep 2022target 2026
Gas project J3155, Winnebago County
Gas
150 MWIn study Winnebago, WIMISO Sep 2022target 2025
Gas project J3151, Sheboygan County
Gas
150 MWIn study Sheboygan, WIMISO Sep 2022target 2025
Solar + storage project J3224, Marion County
Solar + storage
150 MWIn study Marion, ILMISO Sep 2022target 2026
Battery storage project J2203, Adams County
Battery storage
150 MWIn study Adams, ILMISO Mar 2022target 2024
Battery storage project J3009, Washtenaw County
Battery storage
150 MWIn study Washtenaw, MIMISO Aug 2022target 2025
Battery storage project J2454, Montcalm County
Battery storage
150 MWIn study Montcalm, MIMISO Sep 2022target 2025
Battery storage project J2170, Clark County
Battery storage
150 MWIn study Clark, ILMISO Apr 2022target 2024
Solar + storage project J2897, San Jacinto County
Solar + storage
150 MWIn study San Jacinto, TXMISO Sep 2022target 2025
Solar project J2501, Goodhue County
Solar
150 MWIn study Goodhue, MNMISO Sep 2022target 2024
Solar project J2720, Yazoo County
Solar
150 MWIn study Yazoo, MSMISO Sep 2022target 2025
Solar project J2156, Johnson County
Solar
150 MWIn study Johnson, ILMISO Jun 2022target 2024
Battery storage project J2589, Jackson County
Battery storage
150 MWIn study Jackson, MIMISO Sep 2022target 2025
Solar project J2155, New Madrid County
Solar
150 MWIn study New Madrid, MOMISO Mar 2022target 2024
Battery storage project J2473, Marion County
Battery storage
150 MWIn study Marion, INMISO Sep 2022target 2026
Solar project J1638, Hancock County
Solar
150 MWIn study Hancock, KYMISO Feb 2022target 2026
Solar project J1750, Marquette County
Solar
150 MWUnder construction Marquette, MIMISO Apr 2022target 2026
Solar project J1744, Cumberland County
Solar
150 MWIn study Cumberland, ILMISO Apr 2022target 2027
Solar project J1752, Portage County
Solar
148 MWUnder construction Portage, WIMISO May 2022target 2026
Solar project J2861, Mower County
Solar
147 MWIn study Mower, MNMISO Sep 2022target 2029
Solar + storage project J3184, St. Clair County
Solar + storage
145 MWIn study St. Clair, ILMISO Sep 2022target 2027
Battery storage project J3063, Perry County
Battery storage
143 MWIn study Perry, ILMISO Sep 2022target 2026
Solar + storage project J3004, Mason County
Solar + storage
142 MWIn study Mason, ILMISO Sep 2022target 2025
Solar + storage project J3229, Maries County
Solar + storage
140 MWIn study Maries, MOMISO Sep 2022target 2026
Solar project J2901, Columbia County
Solar
140 MWIn study Columbia, ARMISO Sep 2022target 2027
Solar project J2669, Mason County
Solar
140 MWIn study Mason, MIMISO Sep 2022target 2025
Solar project J2815, Calhoun County
Solar
140 MWIn study Calhoun, MIMISO Aug 2022target 2026
Solar + storage project J2619, Montcalm County
Solar + storage
140 MWIn study Montcalm, MIMISO Sep 2022target 2026
Solar + storage project J2593, Gasconade County
Solar + storage
140 MWIn study Gasconade, MOMISO Sep 2022target 2026
Solar project J2812, Hillsdale County
Solar
140 MWIn study Hillsdale, MIMISO Sep 2022target 2026
Solar project J2983, Grant County
Solar
140 MWIn study Grant, ARMISO Sep 2022target 2025
Solar project J2972, Adams County
Solar
140 MWIn study Adams, ILMISO Sep 2022target 2026
Battery storage project J2657, White County
Battery storage
138 MWIn study White, INMISO Sep 2022target 2027
Solar project J1816, Cross County
Solar
135 MWIn study Cross, ARMISO Mar 2022target 2025
Solar + storage project J3082, Franklin Parish County
Solar + storage
135 MWIn study Franklin Parish, LAMISO Sep 2022target 2026
Solar project J2985, Chicot County
Solar
135 MWIn study Chicot, ARMISO Sep 2022target 2025
Surplus; J734
Other
135 MWIn study Mclean, ILMISO Dec 2022target 2026
Solar + storage project J2648, Champaign County
Solar + storage
135 MWIn study Champaign, ILMISO Sep 2022target 2027
Solar project J2809, Iroquois County
Solar
133 MWIn study Iroquois, ILMISO Sep 2022target 2026
Solar project J2885, Red Lake County
Solar
130 MWIn study Red Lake, MNMISO Sep 2022target 2025
Solar project J2307, Miami County
Solar
130 MWIn study Miami, INMISO Mar 2022target 2025
Battery storage project J2343, Marion County
Battery storage
130 MWIn study Marion, INMISO Sep 2022target 2026
Solar + storage project J2738, Rock Island County
Solar + storage
128 MWIn study Rock Island, ILMISO Sep 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)