United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J2749, Polk County
Solar project J2749, Polk County is a 150 MW solar request in interconnection study in the MISO interconnection queue, in Polk County, Minnesota, connecting to OTTER TAIL POWER COMPANY.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2749
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- Winger 115kV
- Location
- Polk County, Minnesota
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- August 2026
Location
Marker shows the centre of Polk County; the queue data does not give exact sites.
Other requests in Polk County
- Solar project J3952, Polk CountySolar · 395 MW · withdrawn
- Onshore wind project J1081, Polk CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J062, Polk CountyOnshore wind · 250 MW · withdrawn
- Solar project J3951, Polk CountySolar · 218 MW · withdrawn
- Onshore wind project H032, Polk CountyOnshore wind · 180 MW · withdrawn
- Onshore wind project MPC01400, Polk CountyOnshore wind · 160 MW · withdrawn
- Solar project J2291, Polk CountySolar · 150 MW · withdrawn
- Solar project J2286, Polk CountySolar · 90.0 MW · withdrawn
- Solar project J1941, Polk CountySolar · 60.0 MW · withdrawn
- Onshore wind project J077, Polk CountyOnshore wind · 50.0 MW · withdrawn
- Battery storage project J2285, Polk CountyBattery storage · 45.0 MW · withdrawn
- Battery storage project J1968, Polk CountyBattery storage · 30.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem