United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · MISOBattery storage project J2473, Marion County
Battery storage project J2473, Marion County is a 150 MW battery storage request in interconnection study in the MISO interconnection queue, in Marion County, Indiana, connecting to INDIANAPOLIS POWER & LIGHT COMPANY.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2473
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- INDIANAPOLIS POWER & LIGHT COMPANY
- Connection point (POI)
- Hanna 138kV
- Location
- Marion County, Indiana
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- September 2026
Location
Marker shows the centre of Marion County; the queue data does not give exact sites.
Other requests in Marion County
- Battery storage project J2343, Marion CountyBattery storage · 130 MW · in study
- Gas project G025, Marion CountyGas · 189 MW · built
- Battery storage project J401, Marion CountyBattery storage · 20.0 MW · built
- Battery storage project J1491, Marion CountyBattery storage · 200 MW · withdrawn
- Battery storage project J2032, Marion CountyBattery storage · 70.0 MW · withdrawn
- Battery storage project J1601, Marion CountyBattery storage · 50.0 MW · withdrawn
- Battery storage project J3709, Marion CountyBattery storage · 47.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem