United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · MISOBattery storage project J401, Marion County
Battery storage project J401, Marion County is a 20.0 MW battery storage request built and operating in the MISO interconnection queue, in Marion County, Indiana.
Request details
- Queue ID
- J401
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Stout South Substation 138
- Location
- Marion County, Indiana
- Technology
- Battery: 20.0 MW
- Total requested
- 20.0 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 10 November 2014
- Agreement signed
- 19 March 2016
- Proposed online date
- January 2016
- Came online
- January 2016
Location
Marker shows the centre of Marion County; the queue data does not give exact sites.
Other requests in Marion County
- Battery storage project J2473, Marion CountyBattery storage · 150 MW · in study
- Battery storage project J2343, Marion CountyBattery storage · 130 MW · in study
- Gas project G025, Marion CountyGas · 189 MW · built
- Battery storage project J1491, Marion CountyBattery storage · 200 MW · withdrawn
- Battery storage project J2032, Marion CountyBattery storage · 70.0 MW · withdrawn
- Battery storage project J1601, Marion CountyBattery storage · 50.0 MW · withdrawn
- Battery storage project J3709, Marion CountyBattery storage · 47.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem