United States βΊ Grid βΊ Interconnection queues βΊ Indiana
BATTERY STORAGE Β· MISOBattery storage project J2032, Marion County
Battery storage project J2032, Marion County is a 70.0 MW battery storage request withdrawn in the MISO interconnection queue, in Marion County, Indiana, connecting to INDIANAPOLIS POWER & LIGHT COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2022 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2032
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- INDIANAPOLIS POWER & LIGHT COMPANY
- Connection point (POI)
- Hanna
- Location
- Marion County, Indiana
- Technology
- Battery: 70.0 MW
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 23 March 2022
- Proposed online date
- October 2025
- Withdrawn
- December 2025
Location
Marker shows the centre of Marion County; the queue data does not give exact sites.
Other requests in Marion County
- Battery storage project J2473, Marion CountyBattery storage Β· 150 MW Β· in study
- Battery storage project J2343, Marion CountyBattery storage Β· 130 MW Β· in study
- Gas project G025, Marion CountyGas Β· 189 MW Β· built
- Battery storage project J401, Marion CountyBattery storage Β· 20.0 MW Β· built
- Battery storage project J1491, Marion CountyBattery storage Β· 200 MW Β· withdrawn
- Battery storage project J1601, Marion CountyBattery storage Β· 50.0 MW Β· withdrawn
- Battery storage project J3709, Marion CountyBattery storage Β· 47.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem