BATTERY STORAGE · MISOBattery storage project J2730, Jackson County
Battery storage project J2730, Jackson County is a 150 MW battery storage request in interconnection study in the MISO interconnection queue, in Jackson County, Minnesota, connecting to ITC MIDWEST.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2730
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Jackson North 161kV Substation
- Location
- Jackson County, Minnesota
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- July 2025
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- Onshore wind project J4099, Jackson CountyOnshore wind · 200 MW · in study
- Other project L009, Jackson CountyOther · -11.0 MW · in study
- Onshore wind project G826, Jackson CountyOnshore wind · 200 MW · built
- Onshore wind project G514, Jackson CountyOnshore wind · 150 MW · built
- Onshore wind project G426, Jackson CountyOnshore wind · 101 MW · built
- Onshore wind project G536, Jackson CountyOnshore wind · 20.0 MW · built
- Onshore wind project G667, Jackson CountyOnshore wind · 13.0 MW · built
- Onshore wind project G518, Jackson CountyOnshore wind · 8.0 MW · built
- Onshore wind project G251, Jackson CountyOnshore wind · 6.0 MW · built
- Onshore wind project J594, Jackson CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J977, Jackson CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project H060, Jackson CountyOnshore wind · 270 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem