Onshore wind project G251, Jackson County

Onshore wind project G251, Jackson County is a 6.0 MW onshore wind request built and operating in the MISO interconnection queue, in Jackson County, Minnesota.

Queue statusOperating
  1. PlanningQueued Jul 2002 (completed)
  2. ConsentedMar 2005 (completed)
  3. Construction (completed)
  4. OperatingJun 2003 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G251
Grid region
MISO (Midcontinent)
Connection point (POI)
Heron Lake - Fox Lake 69kV
Location
Jackson County, Minnesota
Technology
Wind: 6.0 MW
Total requested
6.0 MW
Study phase
SPA - SIS
Queue status
Operational
Entered queue
25 July 2002
Agreement signed
14 March 2005
Proposed online date
June 2003
Came online
June 2003

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem