United States › Grid › Interconnection queues › Minnesota
OTHER · MISOOther project L009, Jackson County
Other project L009, Jackson County is a -11.0 MW other request in interconnection study in the MISO interconnection queue, in Jackson County, Minnesota.
Queue statusIn planning
- PlanningQueued Jan 2005 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2005 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- L009
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Jackson County, Minnesota
- Technology
- Other: -11.0 MW
- Total requested
- -11.0 MW
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 14 January 2005
- Proposed online date
- January 2005
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- Onshore wind project J4099, Jackson CountyOnshore wind · 200 MW · in study
- Battery storage project J2730, Jackson CountyBattery storage · 150 MW · in study
- Onshore wind project G826, Jackson CountyOnshore wind · 200 MW · built
- Onshore wind project G514, Jackson CountyOnshore wind · 150 MW · built
- Onshore wind project G426, Jackson CountyOnshore wind · 101 MW · built
- Onshore wind project G536, Jackson CountyOnshore wind · 20.0 MW · built
- Onshore wind project G667, Jackson CountyOnshore wind · 13.0 MW · built
- Onshore wind project G518, Jackson CountyOnshore wind · 8.0 MW · built
- Onshore wind project G251, Jackson CountyOnshore wind · 6.0 MW · built
- Onshore wind project J594, Jackson CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J977, Jackson CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project H060, Jackson CountyOnshore wind · 270 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem