United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project H060, Jackson County

Onshore wind project H060, Jackson County is a 270 MW onshore wind request withdrawn in the MISO interconnection queue, in Jackson County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedJan 2009 (project stopped here)
  3. ConsentedJan 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H060
Grid region
MISO (Midcontinent)
Connection point (POI)
Jackson - Minowa 161 kV
Location
Jackson County, Minnesota
Technology
Wind: 270 MW
Total requested
270 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
16 June 2008
Agreement signed
20 January 2009
Proposed online date
December 2011
Withdrawn
January 2009

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem