🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G518, Jackson County

Onshore wind project G518, Jackson County is a 8.0 MW onshore wind request built and operating in the MISO interconnection queue, in Jackson County, Minnesota.

Queue statusOperating
  1. PlanningQueued May 2005 (completed)
  2. ConsentedSep 2006 (completed)
  3. Construction (completed)
  4. OperatingOct 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G518
Grid region
MISO (Midcontinent)
Connection point (POI)
Miloma - Round Lake 69 kV
Location
Jackson County, Minnesota
Technology
Wind: 8.0 MW
Total requested
8.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
2 May 2005
Agreement signed
27 September 2006
Proposed online date
October 2007
Came online
October 2007

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem