United States › Grid › Interconnection queues › North Dakota
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in North Dakota — page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project GI-1409, Emmons County Gas |
100 MW | Withdrawn / abandoned |
| Solar project J737, Cass County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project J018, Bowman County Onshore wind |
100 MW | Withdrawn / abandoned |
| Gas project GI-1304, Mckenzie County Gas |
100 MW | Withdrawn / abandoned |
| Onshore wind project J178, Burleigh County Onshore wind |
99.6 MW | Withdrawn / abandoned |
| Onshore wind project GI-0803, Rolette County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project G650, Mountrail County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J150, Mountrail County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0727, Burleigh County Onshore wind · Wilton Wind IV, LLC |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project G951, Sheridan County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0614, Mountrail County Onshore wind · AltaGas Renewable |
99.0 MW | Withdrawn / abandoned |
| Gas project GEN-2023-062, Williams County Gas |
98.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0616, Logan County Onshore wind · Just Wind, LLC |
81.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0211, Dickey County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Battery storage project J2896, Sargent County Battery storage |
80.0 MW | Withdrawn / abandoned |
| Battery storage project GEN-2018-010, Mountrail County Battery storage |
74.1 MW | Withdrawn / abandoned |
| Solar project GEN-2018-039, Lamoure County Solar |
72.0 MW | Withdrawn / abandoned |
| Coal project G531, Mercer County Coal |
68.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0805, Ward County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project G980, Hettinger County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project G845, Cavalier County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project MPC01000, Cass County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Solar project J816, Cass County Solar |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0925, Griggs County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project G916, Sheridan County Onshore wind |
53.0 MW | Withdrawn / abandoned |
| Onshore wind project J779, Emmons County Onshore wind |
51.0 MW | Withdrawn / abandoned |
| Onshore wind project J741, Emmons County Onshore wind |
51.0 MW | Withdrawn / abandoned |
| Onshore wind project G314, Cavalier County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project G659, Oliver County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2017-235, Ward County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Battery storage project GEN-2021-100, Mercer County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project MPC02500, Cass County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project MPC00900, Cass County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project G696, Cass County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2017-236, Ward County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0512, Dickey County Onshore wind |
49.5 MW | Withdrawn / abandoned |
| Onshore wind project GI-0706, Adams County Onshore wind |
48.0 MW | Withdrawn / abandoned |
| Onshore wind project MPC00800, Cass County Onshore wind |
48.0 MW | Withdrawn / abandoned |
| Solar project J2084, Emmons County Solar |
45.0 MW | Withdrawn / abandoned |
| Onshore wind project J1758, Barnes County Onshore wind |
42.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0212, Dickey County Onshore wind |
40.0 MW | Withdrawn / abandoned |
| Solar project J2085, Emmons County Solar |
40.0 MW | Withdrawn / abandoned |
| Onshore wind project J1761, Barnes County Onshore wind |
39.0 MW | Withdrawn / abandoned |
| Solar project GEN-2019-020, Williams County Solar |
35.0 MW | Withdrawn / abandoned |
| Onshore wind project J1763, Cavalier County Onshore wind |
33.0 MW | Withdrawn / abandoned |
| Onshore wind project H022, Barnes County Onshore wind |
33.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-0120, Lamoure County Onshore wind |
30.0 MW | Withdrawn / abandoned |
| Onshore wind project J251, Ramsey County Onshore wind |
27.5 MW | Withdrawn / abandoned |
| Onshore wind project J157, Ramsey County Onshore wind |
27.0 MW | Withdrawn / abandoned |
| Solar project J929, Mcintosh County Solar |
25.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)174 · 30.9 GW
- West (non-ISO utilities)57 · 11.9 GW
- SPP (Southwest Power Pool)53 · 10.7 GW
- PJM (Mid-Atlantic, Midwest)1 · 1,500 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)