Solar project GEN-2018-039, Lamoure County

Solar project GEN-2018-039, Lamoure County is a 72.0 MW solar request withdrawn in the SPP interconnection queue, in Lamoure County, North Dakota, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2018 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-039
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Edgeley 115kV substation
Location
Lamoure County, North Dakota
Technology
Solar: 72.0 MW
Total requested
72.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 May 2018
Proposed online date
December 2028
Withdrawn
March 2024

Location

Marker shows the centre of Lamoure County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Lamoure County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem