BATTERY STORAGE Β· SPP

Battery storage project GEN-2021-100, Mercer County

Battery storage project GEN-2021-100, Mercer County is a 50.0 MW battery storage request withdrawn in the SPP interconnection queue, in Mercer County, North Dakota, connecting to BEPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2021 (completed)
  2. Withdrawn / abandonedJul 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-100
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Leland Olds 345kV substation
Location
Mercer County, North Dakota
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
24 May 2021
Proposed online date
October 2027
Withdrawn
July 2023

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem