ONSHORE WIND Β· WEST

Onshore wind project GI-0614, Mountrail County

Onshore wind project GI-0614, Mountrail County is a 99.0 MW onshore wind request withdrawn in the West interconnection queue, in Mountrail County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0614
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Developer
AltaGas Renewable
Connection point (POI)
Tioga-Logan 230kV
Location
Mountrail County, North Dakota
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Service type
NRIS and ERIS
Study phase
IAE/IAT
Queue status
Withdrawn
Entered queue
18 August 2006
Proposed online date
February 2008

Location

Marker shows the centre of Mountrail County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mountrail County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem