United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
ONSHORE WIND Β· WESTOnshore wind project GI-0803, Rolette County
Onshore wind project GI-0803, Rolette County is a 99.0 MW onshore wind request withdrawn in the West interconnection queue, in Rolette County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-0803
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA/BEPC/HCPD Integrated System
- Connection point (POI)
- Rolla 69kV
- Location
- Rolette County, North Dakota
- Technology
- Wind: 99.0 MW
- Total requested
- 99.0 MW
- Service type
- NRIS and ERIS
- Study phase
- IAP
- Queue status
- Withdrawn
- Entered queue
- 22 January 2008
- Proposed online date
- December 2009
Location
Marker shows the centre of Rolette County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Rolette County
- Onshore wind project J290, Rolette CountyOnshore wind Β· 150 MW Β· built
- Onshore wind project G481, Rolette CountyOnshore wind Β· 1.0 MW Β· built
- Onshore wind project J2019, Rolette CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project G904, Rolette CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project G450, Rolette CountyOnshore wind Β· 1.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem