United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project J2019, Rolette County

Onshore wind project J2019, Rolette County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Rolette County, North Dakota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedNov 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2019
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Rugby-Glenborough 230 kV Line
Location
Rolette County, North Dakota
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3
Queue status
Withdrawn
Entered queue
27 August 2021
Proposed online date
February 2025
Withdrawn
November 2021

Location

Marker shows the centre of Rolette County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Rolette County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem