United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in ISO-NE (New England) — page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery Storage Battery storage |
167 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
167 MW | Withdrawn / abandoned |
| Offshore Wind Increase (Q781) Offshore wind |
167 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
166 MW | Withdrawn / abandoned |
| Solar Solar |
165 MW | Withdrawn / abandoned |
| Converts QP 164 to combined cycle facility and inc Gas |
162 MW | Withdrawn / abandoned |
| Combined Cycle Capacity Increase (See QP #202) Gas |
161 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
160 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
160 MW | Withdrawn / abandoned |
| Gas Turbine Gas |
159 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
158 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
156 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
155 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Solar Solar |
152 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
152 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
152 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
152 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
151 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
151 MW | Withdrawn / abandoned |
| Solar Solar |
150 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Wind Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar Solar |
150 MW | Withdrawn / abandoned |
| Solar Solar |
150 MW | Withdrawn / abandoned |
| Energy Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Wind Alternative (see 272) Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar Solar |
150 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Wind Onshore wind |
150 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Wind Onshore wind |
146 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
143 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
142 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
142 MW | Withdrawn / abandoned |
| Battery Storage Increase (QP1362) Battery storage |
141 MW | Withdrawn / abandoned |
| Gas Turbine Capacity Increase( #157) Gas |
140 MW | Withdrawn / abandoned |
| Solar and Battery Solar + storage |
139 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
136 MW | Withdrawn / abandoned |
| Solar Solar |
135 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
135 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
135 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
134 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
133 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)