United States βΊ Grid βΊ Interconnection queues βΊ Rhode Island
OFFSHORE WIND Β· ISO-NEOffshore Wind Increase (Q781)
Offshore Wind Increase (Q781) is a 167 MW offshore wind request withdrawn in the ISO-NE interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2019 (completed)
- Withdrawn / abandonedNov 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 926
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- National Grid's 115kV Davisville Substation
- Location
- Rhode Island
- Technology
- Offshore Wind: 167 MW
- Total requested
- 167 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 11 September 2019
- Proposed online date
- December 2023
- Withdrawn
- November 2020
Location
No county location in the queue data.
Power plants in Rhode Island Β· Transmission lines in Rhode Island
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem