BATTERY STORAGE · ISO-NE

Energy Storage

Energy Storage is a 150 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Barnstable County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedFeb 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
687
Grid region
ISO-NE (New England)
Connection point (POI)
Falmouth 533 Eversource Energy 115KV
Location
Barnstable County, Massachusetts
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Suspended
Queue status
Withdrawn
Entered queue
21 November 2017
Proposed online date
December 2021
Withdrawn
February 2019

Location

Marker shows the centre of Barnstable County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Barnstable County