BATTERY STORAGE · ISO-NE

Storage

Storage is a 150 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Middlesex County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
761
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid 115 kV line M139
Location
Middlesex County, Massachusetts
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
27 April 2018
Proposed online date
May 2021
Withdrawn
March 2020

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Middlesex County