United States › Grid › Interconnection queues › Massachusetts
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 152 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Bristol County, Massachusetts.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2023 (completed)
- Withdrawn / abandonedSep 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1442
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Primary: Eversource 115 kV Cross Road Line 111, alternate: line 109
- Location
- Bristol County, Massachusetts
- Technology
- Battery: 152 MW
- Total requested
- 152 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 18 September 2023
- Proposed online date
- May 2027
- Withdrawn
- September 2024
Location
Marker shows the centre of Bristol County; the queue data does not give exact sites.
Power plants in Massachusetts · Transmission lines in Massachusetts
Other requests in Bristol County
- Battery StorageBattery storage · 350 MW · in study
- Battery StorageBattery storage · 168 MW · in study
- Brayton Point 3 Uprate( see 243)Coal · 30.0 MW · built
- Dartmouth Power ExpansionGas · 24.0 MW · built
- Increase to Steam Turbine Capacity Uprate (See QPCoal · 6.0 MW · built
- Dighton Power UprateGas · 5.0 MW · built
- SolarSolar · 1.9 MW · built
- Combined CycleGas · 550 MW · withdrawn
- Battery StorageBattery storage · 529 MW · withdrawn
- Battery StorageBattery storage · 293 MW · withdrawn
- Battery StorageBattery storage · 271 MW · withdrawn
- Battery StorageBattery storage · 257 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem