United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 158 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Worcester County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandonedMay 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1298
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 345 kV Line 3361, approximately 3.2 miles from Sherman Road and 7.6 miles from Blackstone.
Location
Worcester County, Massachusetts
Technology
Battery: 158 MW
Total requested
158 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
16 August 2022
Proposed online date
June 2027
Withdrawn
May 2024

Location

Marker shows the centre of Worcester County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Worcester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem