United States › Grid › Interconnection queues › Rhode Island
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 166 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Providence County, Rhode Island.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2024 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1548
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Primary POI: 42.001693, -71.710650, Eversource Line 347, Sherman Road to Killingly 345kV Alternate POI: 42.001693, -71.710650, Eversource West Farnum to Lake Road 345kV
- Location
- Providence County, Rhode Island
- Technology
- Battery: 166 MW
- Total requested
- 166 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 May 2024
- Proposed online date
- March 2028
- Withdrawn
- October 2024
Location
Marker shows the centre of Providence County; the queue data does not give exact sites.
Power plants in Rhode Island · Transmission lines in Rhode Island
Other requests in Providence County
- Ocean State Power uprateGas · 73.2 MW · agreement signed
- Manchester Street Station increaseGas · 492 MW · built
- RISEP IncreaseGas · 66.0 MW · built
- GD 1-9 Iron Mine SolarSolar · 38.4 MW · built
- Rhode Island Landfill Gas GencoOther · 27.9 MW · built
- Johnston Landfill WindOnshore wind · 21.0 MW · built
- SolarSolar · 16.3 MW · built
- Manchester Street Station Exciter Upgrades & increGas · 12.0 MW · built
- SolarSolar · 10.0 MW · built
- Ridgewood RI Generation Phase IOther · 4.2 MW · built
- Clear RiverGas · 1,030 MW · withdrawn
- Exciter UpgradesGas · 492 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem