ONSHORE WIND Β· ISO-NE

Wind

Wind is a 150 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Franklin County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedFeb 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
744
Grid region
ISO-NE (New England)
Connection point (POI)
Approximate location of the proposed Point of Interconnection is the CMP Avangrid Larrabee Road 345 kV Substation
Location
Franklin County, Maine
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
12 April 2018
Proposed online date
December 2022
Withdrawn
February 2019

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem