United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2016 requests) โ€” page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,194150.9 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,194 requests ยท page 4 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-544, Laurens County
Solar
240 MWWithdrawn / abandoned Laurens, GASoutheast Nov 2016
Onshore wind project GEN-2016-103, Hyde County
Onshore wind
240 MWWithdrawn / abandoned Hyde, SDSPP Nov 2016target 2018
Helios Secondus
Solar
232 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2020
Onshore wind project GEN-2016-172, Castro County
Onshore wind
231 MWWithdrawn / abandoned Castro, TXSPP Nov 2016target 2018
Cumberland
Gas
230 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2016target 2023
Onshore wind project GEN-2016-096, Fillmore County
Onshore wind
228 MWWithdrawn / abandoned Fillmore, NESPP Nov 20162020
Gas project 53, Pima County
Gas
226 MWWithdrawn / abandoned Pima, AZWest Nov 2016target 2018
Onshore wind project GEN-2016-122, Ellsworth County
Onshore wind
225 MWWithdrawn / abandoned Ellsworth, KSSPP Nov 20162020
Onshore wind project J593, Williams County
Onshore wind
224 MWWithdrawn / abandoned Williams, NDMISO May 2016target 2018
Onshore wind project GEN-2016-112, Ellsworth County
Onshore wind
220 MWWithdrawn / abandoned Ellsworth, KSSPP Nov 20162020
Onshore wind project GEN-2016-073, Kingman County
Onshore wind
220 MWWithdrawn / abandoned Kingman, KSSPP Mar 20162025
Wind
Onshore wind
216 MWWithdrawn / abandoned Franklin, MEISO-NE Jan 2016target 2019
Solar project IC-537, Jeff Davis County
Solar
215 MWWithdrawn / abandoned Jeff Davis, GASoutheast Nov 2016
Solar project IC-442, Jackson County
Solar
213 MWWithdrawn / abandoned Jackson, FLSoutheast Feb 2016
Solar project GEN-2016-058, Yoakum County
Solar
212 MWWithdrawn / abandoned Yoakum, TXSPP Mar 2016target 2018
Onshore wind project J742, Cottonwood County
Onshore wind
211 MWWithdrawn / abandoned Cottonwood, MNMISO Nov 2016target 2020
Barstow Solar 1
Solar
211 MWWithdrawn / abandoned San Bernardino, CACAISO May 2016target 2021
Re Prism
Solar
209 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2019
Mount Laguna Wind
Onshore wind
208 MWWithdrawn / abandoned San Diego, CACAISO May 2016target 2023
Coso Solar 2
Solar
207 MWWithdrawn / abandoned Inyo, CACAISO May 2016target 2019
Rolling Hills Solar
Solar
206 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2020
Romero Creek
Wind + storage
206 MWWithdrawn / abandoned Merced, CACAISO May 2016target 2023
South Ridge
Solar
205 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2021
Ghost Town Solar
Solar
205 MWWithdrawn / abandoned San Bernardino, CACAISO May 2016target 2020
Red Wing Ranch Solar
Solar
205 MWWithdrawn / abandoned Yuma, AZCAISO May 2016target 2021
Blue Wing Ranch Solar
Solar
205 MWWithdrawn / abandoned Yuma, AZCAISO May 2016target 2021
Onshore wind project J638, Deuel County
Onshore wind
204 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2019
LH Energy Storage
Battery storage
204 MWWithdrawn / abandoned Los Angeles, CACAISO May 2016target 2020
Seis Puntos Solar
Solar
203 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2018
Soda Lake Solar 1
Solar ยท Arrington Solar
203 MWWithdrawn / abandoned Crane, TXERCOT Oct 2016target 2023
Onshore wind project GEN-2016-165, Knox County
Onshore wind
202 MWWithdrawn / abandoned Knox, NESPP Nov 2016target 2019
Solar project J567, Iberville Parish County
Solar
202 MWWithdrawn / abandoned Iberville Parish, LAMISO May 2016target 2019
Darmstadt
Onshore wind ยท RES Americas
201 MWWithdrawn / abandoned Schleicher, TXERCOT Jun 2016target 2021
Onshore wind project GEN-2016-127, Osage County
Onshore wind
200 MWWithdrawn / abandoned Osage, OKSPP Nov 2016target 2019
Onshore wind project AC1-226, Pulaski County
Onshore wind
200 MWWithdrawn / abandoned Pulaski, VAPJM Oct 2016target 2019
Onshore wind project J755, Bowman County
Onshore wind
200 MWWithdrawn / abandoned Bowman, NDMISO Nov 2016target 2019
Yellow Jacket Wind
Onshore wind ยท RES Americas
200 MWWithdrawn / abandoned ERCOT Dec 2016target 2019
Solar project 49, Pima County
Solar
200 MWWithdrawn / abandoned Pima, AZWest Sep 2016target 2019
Solar project Q241, Yavapai County
Solar
200 MWWithdrawn / abandoned Yavapai, AZWest Mar 2016target 2019
Solar project GI-2016-5, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Apr 2016target 2019
Onshore wind project GI-58, Kingfisher County
Onshore wind
200 MWWithdrawn / abandoned Kingfisher, OKSoutheast Jul 2016target 2018
Onshore wind project J602, Shiawassee County
Onshore wind
200 MWWithdrawn / abandoned Shiawassee, MIMISO May 2016target 2021
Solar project Q234, Maricopa County
Solar
200 MWWithdrawn / abandoned Maricopa, AZWest Mar 2016target 2021
Onshore wind project J731, Palo Alto County
Onshore wind
200 MWWithdrawn / abandoned Palo Alto, IAMISO Nov 2016target 2020
Onshore wind project GEN-2016-012, Anderson County
Onshore wind
200 MWWithdrawn / abandoned Anderson, KSSPP Mar 2016target 2018
Solar project 293, Panola County
Solar
200 MWWithdrawn / abandoned Panola, MSSoutheast May 2016
Onshore wind project J746, Mchenry County
Onshore wind
200 MWWithdrawn / abandoned Mchenry, NDMISO Nov 2016target 2020
Onshore wind project J740, Jasper County
Onshore wind
200 MWWithdrawn / abandoned Jasper, INMISO Nov 2016target 2020
Onshore wind project J733, Franklin County
Onshore wind
200 MWWithdrawn / abandoned Franklin, IAMISO Nov 2016target 2020
Solar project AC1-150, Pike County
Solar
200 MWWithdrawn / abandoned Pike, OHPJM Oct 2016target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)