Solar project Q241, Yavapai County

Solar project Q241, Yavapai County is a 200 MW solar request withdrawn in the West interconnection queue, in Yavapai County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q241
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Round Valley 230kV Substation
Location
Yavapai County, Arizona
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
30 March 2016
Proposed online date
December 2019

Location

Marker shows the centre of Yavapai County; the queue data does not give exact sites.