United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· MISO

Onshore wind project J740, Jasper County

Onshore wind project J740, Jasper County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Jasper County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedAug 2020 (project stopped here)
  3. ConsentedMar 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J740
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
Reynold 345kV substation
Location
Jasper County, Indiana
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Withdrawn
Queue status
Withdrawn
Entered queue
11 November 2016
Agreement signed
15 March 2019
Proposed online date
October 2020
Withdrawn
August 2020

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Jasper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem