United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J731, Palo Alto County

Onshore wind project J731, Palo Alto County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Palo Alto County, Iowa, connecting to MIDAMERICAN ENERGY COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J731
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY COMPANY
Connection point (POI)
Kossuth-O'Brien 345kV
Location
Palo Alto County, Iowa
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
8 November 2016
Proposed online date
September 2020
Withdrawn
April 2019

Location

Marker shows the centre of Palo Alto County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Palo Alto County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem