United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project J529, Palo Alto County
Onshore wind project J529, Palo Alto County is a 250 MW onshore wind request built and operating in the MISO interconnection queue, in Palo Alto County, Iowa.
Request details
- Queue ID
- J529
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Obrien - Kossuth 345 kV line
- Location
- Palo Alto County, Iowa
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Study phase
- GIA
- Queue status
- Operational
- Entered queue
- 16 November 2015
- Agreement signed
- 12 March 2019
- Proposed online date
- July 2018
- Came online
- July 2018
Location
Marker shows the centre of Palo Alto County; the queue data does not give exact sites.
Other requests in Palo Alto County
- Solar project J877, Palo Alto CountySolar · 250 MW · under construction
- Onshore wind project J3324, Palo Alto CountyOnshore wind · 200 MW · in study
- Onshore wind project J1270, Palo Alto CountyOnshore wind · 200 MW · in study
- Onshore wind project J590, Palo Alto CountyOnshore wind · 90.0 MW · built
- Onshore wind project J731, Palo Alto CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GI-0612a, Palo Alto CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GI-0807a, Palo Alto CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GI-0703a, Palo Alto CountyOnshore wind · 101 MW · withdrawn
- Onshore wind project G554, Palo Alto CountyOnshore wind · 100 MW · withdrawn
- Other project G317, Palo Alto CountyOther · 80.0 MW · withdrawn
- Onshore wind project J938, Palo Alto CountyOnshore wind · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem