Barstow Solar 1

Barstow Solar 1 is a 211 MW solar request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1308
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Coolwater Substation 115kV
Location
San Bernardino County, California
Technology
Solar: 211 MW
Total requested
211 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 May 2016
Proposed online date
June 2021
Withdrawn
March 2019

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem