πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2016-122, Ellsworth County

Onshore wind project GEN-2016-122, Ellsworth County is a 225 MW onshore wind request withdrawn in the SPP interconnection queue, in Ellsworth County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedFeb 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2020 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-122
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Reno - Summit 345kV
Location
Ellsworth County, Kansas
Technology
Wind: 225 MW
Total requested
225 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2016
Proposed online date
December 2020
Came online
December 2020
Withdrawn
February 2021

Location

Marker shows the centre of Ellsworth County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Ellsworth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem