United States βΊ Grid βΊ Interconnection queues βΊ Kansas
ONSHORE WIND Β· SPPOnshore wind project GEN-2016-122, Ellsworth County
Onshore wind project GEN-2016-122, Ellsworth County is a 225 MW onshore wind request withdrawn in the SPP interconnection queue, in Ellsworth County, Kansas, connecting to WERE.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2016 (completed)
- Withdrawn / abandonedFeb 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2020 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2016-122
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WERE
- Connection point (POI)
- Reno - Summit 345kV
- Location
- Ellsworth County, Kansas
- Technology
- Wind: 225 MW
- Total requested
- 225 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 November 2016
- Proposed online date
- December 2020
- Came online
- December 2020
- Withdrawn
- February 2021
Location
Marker shows the centre of Ellsworth County; the queue data does not give exact sites.
Other requests in Ellsworth County
- Onshore wind project GEN-2018-047, Ellsworth CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2016-112, Ellsworth CountyOnshore wind Β· 220 MW Β· withdrawn
- Onshore wind project GEN-2018-123, Ellsworth CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2016-113, Ellsworth CountyOnshore wind Β· 155 MW Β· withdrawn
- Onshore wind project GEN-2017-035, Ellsworth CountyOnshore wind Β· 85.0 MW Β· withdrawn
- Onshore wind project GEN-2017-034, Ellsworth CountyOnshore wind Β· 25.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem