United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2016-113, Ellsworth County

Onshore wind project GEN-2016-113, Ellsworth County is a 155 MW onshore wind request withdrawn in the SPP interconnection queue, in Ellsworth County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-113
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Reno (GEN-2016-111 Tap)-Summit 345kV
Location
Ellsworth County, Kansas
Technology
Wind: 155 MW
Total requested
155 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2016
Proposed online date
December 2018
Withdrawn
April 2020

Location

Marker shows the centre of Ellsworth County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Ellsworth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem